Inspections

  1. Excavation / Footing– For piers and pads prior to placing concrete, our inspector will confirm that the foundation system is constructed as per the Ontario Building Code and the approved plans.
  2. Framing– Required at completion of structural framing prior to installation of decking.
  3. Final– Required at completion of decking, stairs and guards.

Any proposed changes from the approved design must be approved by the building department prior to construction.

Failure to have the required inspections performed may result in the owner having to uncover and expose the work for inspection, Orders Issued, etc….

For more information, visit: Building & Planning Services | Municipal Services | Town of Mattawa

 

  • Notching railing posts.
  • Use of improper, split or undersized pickets in guards.
  • Improper spacing between pickets in guards.
  • Splicing of beams not over supports.
  • Use of unauthorized material or systems.
  • Unauthorized changes from permit drawings.